A Complex Install

I carried out the initial visit in November 2013 and we were awarded the contract in December .We installed the first week in January and handed over within 2 weeks including all service connection ,drainage ,carpets etc .This was a really awkward install ,we laid a steel road inside the school to protect the playground and contracted two cranes two carryout the install .The lorries were parked in the road ( a parking suspension had to be put in place by mrc) we then managed the traffic and lifted the loads from the road via a 50 tonne crane which lifted to An 80 tonne crane further in the site ,this then lifted over a four storey building where we placed the building on wheels and towed into its final location.This building is on hire and will come out the same way in 18 months time
MRC carried out an initial visit to Kensington School, London in November 2013 for the installation of one of our modular buildings. We were awarded the contract in December where we installed the building during the first week in January and handed over within 2 weeks including all service connection, drainage, carpets etc.
This was a challenging install as we had to lay a steel road inside the school to protect the playground and contracted two cranes to carry out the install. The lorries were parked in the road (a parking suspension had to be put in place by MRC) we then managed the traffic and lifted the loads from the road via a 50 tonne crane which lifted to An 80 tonne crane further in the site, this then lifted over a four storey building where we placed the building on wheels and towed into its final location.
This building is on hire and will come out the same way in 18 months time.